Information Technology A to Z Index

Banner 9

Banner 9

Upgrade from Banner 8.x to Banner 9.x

IT has begun a year long project to upgrade Banner 8 to Banner 9.   This will include upgrading the Administrative piece of Banner (formerly Banner Forms) and Banner Self-Service (formerly EKUDirect).   Ellucian is requiring all Banner schools to be completely on Banner 9 by December 30, 2018.  According to Ellucian, "Banner 9 by Ellucian is no ordinary upgrade.  It delivers a fresh user experience, all new tools, and significantly improved capabilities across Banner, driving new efficiencies so you can focus on student success."   

EKU Timeline - subject to change

** Admin Pages are equivalent to Banner 8 INB forms

** EKU Direct upgrade TBD

  • June 2017
    • Test Environment
      • Banner 8 to Banner 9 Single Sign-On -- COMPLETE
      • Application Navigator -- COMPLETE
  • July 2017
    • Production Environment
      • Banner 8 to Banner 9 Single Sign-On -- Go Live in November/December, see below
  • Test Environment
    • General Administrative Pages -- COMPLETE
    • HR Administrative Pages -- COMPLETE
    • Begin IT organized training -- IN PROGRESS
  • August - October 2017
    • Test Environment
      • Student Administrative Pages -- COMPLETE
      • Financial Aid Administrative Pages -- COMPLETE
      • Finance Administrative Pages -- COMPLETE
      • Advancement Administrative Pages -- COMPLETE
      • IT staff and End Users begin training with their systems -- IN PROGRESS
  • November - December 2017
    • ​Production Environment
      • Banner 9 General will go live in Production -- delayed to March
      • Application Navigator in Production (Banner 8 will move to Application Navigator. Communication will be sent to users regarding Banner 8 and Application Navigator) -- delayed to March
  • November 2017 - February 2018
    • Test Environment
      • Continue training, Go Live testing completed prior to each module's Go Live date
  • March - April 2018
    • Production Environment
      • General & Application Navigator Go Live (COMPLETE) -- week of March 19th or 26th
      • Finance Go Live (COMPLETE) -- April 9th
      • Student Go Live (COMPLETE) -- April 16th
      • Financial Aid Go Live (tentative) -- April 30th
      • Accounts Receivable Go Live (tentative) -- April 30th
  • May 2018
    • Production Environment
      • TBD
  • June 30, 2018
    • Production Environment
      • Advancement Go Live -- June 4th
      • Human Resources/Payroll Go Live -- June 5th
      • Conversion Complete, Banner 9 conversion celebration TBD