Banner 9

Upgrade from Banner 8.x to Banner 9.x

IT has begun a year long project to upgrade Banner 8 to Banner 9.   This will include upgrading the Administrative piece of Banner (formerly Banner Forms) and Banner Self-Service (formerly EKUDirect).   Ellucian is requiring all Banner schools to be completely on Banner 9 by December 30, 2018.  According to Ellucian, "Banner 9 by Ellucian is no ordinary upgrade.  It delivers a fresh user experience, all new tools, and significantly improved capabilities across Banner, driving new efficiencies so you can focus on student success."   

EKU Timeline - subject to change

** Admin Pages are equivalent to Banner 8 INB forms

** EKU Direct upgrade TBD, tentative upgrades in Test to begin Fall 2017

  • June 2017
    • Test Environment
      • Banner 8 to Banner 9 Single Sign-On -- COMPLETE
      • Application Navigator -- COMPLETE
  • July 2017
    • Production Environment
      • Banner 8 to Banner 9 Single Sign-On -- Go Live in November/December, see below
      • Application Navigator -- Go Live in November/December, see below
    • Test Environment
      • General Administrative Pages -- COMPLETE
      • HR Administrative Pages -- COMPLETE
      • Begin IT organized training -- IN PROGRESS
  • August - October 2017
    • Test Environment
      • Student Administrative Pages -- COMPLETE
      • Financial Aid Administrative Pages -- COMPLETE
      • Finance Administrative Pages -- COMPLETE
      • Advancement Administrative Pages -- COMPLETE
      • IT staff and End Users begin training with their systems
  • November - December 2017
    • ​Production Environment
      • Banner 9 General will go live in Production
      • Application Navigator in Production (Banner 8 will move to Application Navigator. Communication will be sent to users regarding Banner 8 and Application Navigator)
  • November 2017 - February 2018
    • Test Environment
      • Continue training, Go Live testing completed by end of February
    • Production Environment
      • Continue moving areas who have finished Go Live testing
  • March - April 2018
    • Production Environment
      • Finish moving remaining areas to Production
  • June 30, 2018
    • Conversion Complete, Banner 9 conversion celebration TBD

 

Helpful Tips

Documentation

Please check back for updates.

 